Iloilo City underground cabling project nears completion
Come December, the one-kilometer stretch of the old business district along J.M. Basa Street, including its heritage zone Calle Real, will have an enhanced look as the Underground Distribution System (UDS) is nearing completion. Roel Castro, More Electric and Power Corporation (MORE Power) president and chief executive officer, on Monday said the project is on target, they are done with the civil works, and the electrical is 70 percent completed. ‘The challenge is the other utilities like the telecommunication to transfer their lines. But as far as our lines are concerned, they are no longer in the stretch by December.