Red and Yellow Alerts Issued Over Visayas Grid Due to Power Supply Shortage

Doha:Visayas The continued unavailability of several power plants in the Visayas has resulted in a red alert for the grid on Wednesday, from 5 p.m. to 6 p.m.

According to Philippines News Agency, a yellow alert is also in place from 3 p.m. to 5 p.m. and from 6 p.m. to 9 p.m., as stated by the National Grid Corporation of the Philippines (NGCP) in an advisory.

The NGCP reported that the available capacity in the grid is around 2,501 megawatts (MW) while peak demand is expected to reach 2,529MW. The limited capacity is attributed to the unplanned outage of Unit 2 of Therma Visayas Inc. (TVI) and the reduced capacity of TVI Unit 1, the reduced capacity of Unit 3 of the Panay Energy Development Corporation, the planned outage of the Palm Concepcion Power Corporation and Unit 2 of KEPCO SPC Power Corporation, and the tripping of the Leyte A-Mahanagdong A Unit 1.

A total of nine power plants are on forced outage this month alone, while over ten have been non-operational since 2021. Additionally, 21 others are operating at reduced capacities, leading to a total loss of 753.3MW.

The NGCP issues a yellow alert when capacity is short against contingency requirements, while a red alert is issued when capacity is insufficient to meet consumer demand and the grid's regulating requirements.